GRIDCo completes 4km transmission line to connect Yendi Solar Farm to national grid

Screenshot 2026 09 25 033453.png The completed connection will allow electricity to be transmitted into Ghana’s wider power network

Fri, 25 Sep 2026 Source: peacefmonline.com

The Ghana Grid Company Limited (GRIDCo) has completed the construction and final integration of a 4-kilometre, 161-kilovolt (kV) transmission line connecting a solar power project in Yendi to the Tamale-Yendi transmission network.

The project is expected to facilitate the integration of the Bui Power Authority’s 50-megawatt (MW) Yendi Solar Farm into Ghana’s national transmission system ahead of its anticipated opening.

According to GRIDCo, its in-house technical teams executed the transmission project entirely, making it the longest transmission line project the company has completed internally to date.

As part of the project, GRIDCo’s technical teams also integrated a 66-megavolt-ampere (MVA) transformer into the transmission system.

The company said the project drew on expertise from several of its technical units and demonstrated GRIDCo’s capacity to undertake major transmission infrastructure projects using its internal technical resources.

GRIDCo said the new Yendi transmission link would strengthen the national grid’s capacity to accommodate renewable energy and support the expansion of solar power generation in northern Ghana.

The completed connection will allow electricity generated by the Yendi solar project to be transmitted into Ghana’s wider power network, helping integrate additional renewable energy into the national electricity supply system.