Ghana Grid Company Limited (GRIDCo) has written to the Power Distribution Service (PDS) to request for load shedding from 8.00hrs to 18.00hrs each day on affected PDS MV/LV lines.
The request for load shedding on PDS MV/LV lines was necessary due to the diversion of 330KV Aboadze-Volta transmission line at Pokuase to facilitate the interchange construction works being undertaken by the department of Urban Roads at Pokuase.
In a letter cited by GhanaWeb on March 14, 2019, GRIDCo noted that the work was originally planned to be completed by March 14, 2019, but some challenges encountered by the contractor during the execution of the work has made them envisage that the work will be completed by March 19, 2019.
"We, therefore, wish to request you to extend the outage on affected PDS MV/LV lines in the corridor to March 19, 2018. The outage should be from 8.00hrs to 18.00 each day over the period," the statement reads on.
Some parts of the capital were hit by total blackout popularly known as ‘dumsor’ for 3 consecutive days after the takeover PDS.
According to them, this was due to some technical challenges upstream at their Mallam and Graphic Road Bulk Supply Point (BSP) and it has affected power outages within the Western and the Central parts of Accra and they assured that power will be restored immediately the technical challenges are resolved.
Read full statement below
- Invoices on debt payment to IPPs could reach $450 million by end of 2024 - Report
- ECG, GRIDCo collaborate to boost power supply in Ashanti region
- Unveiling the myths around the recent intermittent power shortage on the grid
- Millennium Challenge Corporation halts $190 million funding for Ghana's energy sector
- #DumsorMustStop: Yvonne Nelson notifies IGP of intention to hold dumsor vigil on May 25
- Read all related articles