Photo of work in progress on the road
Rehabilitation of the Atimpoku–Asikuma Junction Road (Lots 1 & 2) are 67.50% and 41% complete, respectively, and ahead of schedule. The projects began in December 2025 and are scheduled for completion in December 2027.
The Minister for Roads and Highways, Kwame Agbodza, inspected progress as part of his working tour of the Eastern Corridor, Upper East, Upper West, Savannah, Volta, Oti and Eastern Regions.
The contractors Ussuya GH Ltd and Dwawill Ltd are currently undertaking construction of drainage systems, widening, subbase and base formation, and filling to formation.
“President Mahama is beginning to see the results of the investment in the Big Push Programme, and we intend to make sure that he succeeds,” the Minister said as he commended the contractors for their professionalism and the quality of their work
He also entreated the contractors to make improvements to bad sections of the road to make it more motorable ahead of the Christmas festivities.