Were working to end "dumsor"- Energy Ministry

The Energy Ministry has given the assurance that it is working assiduously to put an end to the current load shedding Ghanaians are enduring.

A statement signed by the Head of Communications at the Ministry Edward Bawa said the ministry is working together with the various power agencies to put an immediate end to the problem.

The ministry attributes the current challenge to three main factors outlined below:

  1.  Poor inflows of water into our hydro dams,


  2.  Erratic fuel supply from Nigeria


  3.  Non-availability of some generating units due to periodic maintenance.


It, however, provides the following strategies to fix the problem:



The Ministry takes this opportunity to express its appreciation to Ghanaians for their understanding, even in the face of these temporal difficulties and wishes to promise that we will continuously work around the clock until this perennial challenge is eliminated.
Source: starrfmonline.com