The Electricity Company of Ghana has released the timetable for a planned load shedding exercise expected to take place from May 10 to 17, 2021, within some areas in the Greater Accra Region.
The eight-day exercise has become necessary due to ongoing works at the Pokuase Bulk Supply Point.
The project, when completed, is expected to serve 350,000 households.
Chief Executive Officer of ECG, Kwame Agyeman Budu, addressing the media on the issue said four major areas within the Greater Accra Region would have their power supply interrupted.
“We are coming up with a planned schedule for the areas that are going to be affected. The areas have been grouped into four. It has been scheduled in such a way that no single customer will see the outage throughout for the eight days. They will see probably 12 hours outage in the day time; the next three days they will experience the outage in the night time. It will be rotated,” he said.
- I’ll be the first to join Yvonne Nelson’s vigil if 'dumsor’ persists – Sidney
- Improve energy sector governance to address power challenges - IMF to Ghana
- Unilever 'tea operation leaving Ghana has nothing to do with dumsor' - MD
- I sleep beside my ‘widely-open’ fridge – Keche Andrew on how he deals with heat during ‘dumsor’
- DumsorVigil organisers and police hit a snag on decision to use Revolution Square for exercise
- Read all related articles